If a 10% waste factor is applied, how does the required order quantity compare to the exact slab volume?

Prepare for the Concrete Flatwork Technician and Flatwork Finisher Test. Use flashcards and multiple-choice questions with hints and explanations to enhance your study. Ace your exam!

Multiple Choice

If a 10% waste factor is applied, how does the required order quantity compare to the exact slab volume?

Explanation:
You add a waste factor to ensure you have enough concrete to cover losses from spillage, trimming, and placement issues. A 10% waste factor means you increase the exact slab volume by 10%. In practical terms, you multiply the exact volume by 1.10, so the order quantity is 1.10 times the exact volume. For example, if the exact slab volume is 100 cubic yards, you’d order 110 cubic yards. This is why the required order quantity increases by 10%. The other options would under- or over-shoot what’s needed and don’t reflect adding a waste allowance.

You add a waste factor to ensure you have enough concrete to cover losses from spillage, trimming, and placement issues. A 10% waste factor means you increase the exact slab volume by 10%. In practical terms, you multiply the exact volume by 1.10, so the order quantity is 1.10 times the exact volume. For example, if the exact slab volume is 100 cubic yards, you’d order 110 cubic yards. This is why the required order quantity increases by 10%. The other options would under- or over-shoot what’s needed and don’t reflect adding a waste allowance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy